What additional protective equipment will you use when brazing systems containing HC refrigerants?


Ear defenders
A high-visibility vest
A flammable gas detector
Latex gloves

2

Ťažká

Why can’t a sealed high-pressure switch be replaced with a standard mechanical one in a system containing a flammable refrigerant?


Dust and moisture may enter
There is a risk of refrigerant leakage
It is a potential source of ignition
The pressure switch setting will not be correct

3

Ťažká

What is the minimum (recommended) distance from a work area with HC refrigerants within which there must be no sources of ignition?


3 m
0.5 m
2 m
1 m

4

Ťažká

What is the maximum safe R32 fill of a recovery cylinder approved for flammable gas that holds 20 kg of R410A (the liquid density of R32 is about 8-10% lower)?


33 kg
20 kg
18 kg
9 kg

5

Ťažká

What is the maximum charge of an A3 refrigerant for a hermetic display cabinet with an integral condenser located in the ground-floor sales area of a supermarket?


0,494 kg
1.0 kg
10 kg
2.5 kg

6

Ťažká

How can a vacuum pump be used safely to evacuate a system containing a flammable refrigerant?


Ignition-source-free pump, good ventilation, exhaust to a safe place
Place the pump directly on the floor, as low as possible
Such systems need not be evacuated before charging
Position the pump at least 3 m above floor level

7

Ťažká

What safety measure must you carry in your vehicle when transporting flammable refrigerant cylinders?


A fire extinguisher
Tinted safety goggles
Thick gloves
A fire blanket

8

Ťažká

How would you prepare a 10 kg R32 water chiller located outdoors for debrazing its joints?


Vent the R32 outdoors and purge the system
Recover the R32 to a vacuum and start desoldering immediately
Recover the R32 to a vacuum, then fill the system with nitrogen to a slight positive pressure (approx. 0.1 bar g)
Vent the R32 outdoors, then fill and vent the system with nitrogen three times

9

Stredne ťažká

What is R1270?


n-Butane
Propane
Propene (propylene)
Isobutane

10

Ťažká

Which of the following leak detection methods should NOT be used to locate an HC refrigerant leak?


Leak detection foam
Soapy water solution
Electronic leak detector for flammable refrigerants
Electronic HFC leak detector

11

Ťažká

What is the most important difference between a flammable refrigerant recovery unit and a standard one?


A flammable refrigerant recovery unit has no ignition sources
Different connection sizes
A different colour for the station
Different low-pressure switch setting

12

Ťažká

Which of the following is a source of ignition?


An 'n'-type (non-sparking) thermostat
An Ex-certified fan motor
A contactor (sparking contacts)
A sealed NTC temperature sensor

13

Ťažká

What particularly hazardous substance is formed when R32 burns?


Hydrogen fluoride (HF)
Hydrogen chloride (HCl)
Sulphur dioxide (SO₂)
Phosgene

14

Ťažká

What type of refrigerant is R1234ze(E)?


HCFC (hydrochlorofluorocarbon)
CFC (chlorofluorocarbon)
HFO (hydrofluoroolefin)
HC (hydrocarbon)

15

Ťažká

What hazards does a safety group A3 refrigerant pose?


Lower toxicity, higher flammability
Higher toxicity, moderate flammability
Lower toxicity, moderate flammability
Higher toxicity, higher flammability

16

Ťažká

According to EN 378, what is the maximum R290 charge in a cold room measuring 5 m × 3 m × 2.5 m (LFL of R290 = 0.038 kg/m³, access category a, location class I, no additional measures))?


4.93 kg
0.285 kg
1.0 kg
1.5 kg

17

Ťažká

What is the approximate ratio of the volumetric cooling capacity of R32 to that of R410A (same compressor and conditions)?


approx. 1.3
approx. 0.6
approx. 0.75
approx. 1.05–1.1

18

Ťažká

Why are Ex-certified evaporator fan motors used in some systems with flammable refrigerants?


To avoid a source of ignition in the event of a flammable refrigerant leak
Because they must be kept running continuously to disperse the leaking refrigerant
Because they are more energy-efficient
Because they are more reliable

19

Ťažká

Why is the density difference between HC and HFC refrigerants important?


Because HCs operate at much higher pressures
An HC charge in kg is roughly half that of an HFC
Because it determines the system's energy efficiency
Because HCs must be charged much more slowly than HFCs

20

Ťažká

What is the GWP of R290 according to Annex VI to Regulation (EU) 2024/573?


0.02
7
150
675

21

Ťažká

Which of the following is NOT a source of ignition?


An unsealed mechanical pressure switch
A light switch
An Ex-certified fan motor
An electrical switch

22

Ťažká

What is R290?


Isobutane
Butane
Propane
Propene (Propylene)

23

Ťažká

What is the maximum A2L charge for a hermetic display cabinet with integral condenser in the ground-floor sales area of a supermarket?


2.5 kg
150 g
1.5 kg
1.2 kg

24

Ťažká

Why can’t a standard relay be fitted when retrofitting a compressor’s electrical system for flammable refrigerants?


A relay is never required for compressors using flammable refrigerants
Current consumption differs for compressors using flammable refrigerants compared to those using HFCs
The method of starting the compressor motor differs from that used with HFCs
It could be a source of ignition

25

Ťažká

What is the minimum (recommended) distance from a work area with HC refrigerants within which there must be no ignition sources?


1 m
3 m
10 m
5 m

26

Ťažká

A recovery cylinder holds 10 kg of R404A (filling ratio 0.82 kg/l). What is the maximum R290 charge for this cylinder (propane filling ratio 0.43 kg/l per ADR P200)?


approx. 17 kg
approx. 8 kg
approx. 5.2 kg
20 kg

27

Ťažká

How can a vacuum pump be used safely to evacuate a system containing R290?


R290 systems need not be evacuated before charging
Ignition-source-free pump, good ventilation, exhaust to a safe place
Position the pump at least 3 m above floor level
Place the pump directly on the floor, as low as possible

28

Ťažká

Under ADR, what equipment must you carry in your vehicle when transporting flammable refrigerant cylinders (under the 1.1.3.6 exemption)?


Thick gloves
A fire blanket
Tinted safety goggles
A fire extinguisher (at least 2 kg dry powder)

29

Ťažká

How do you make sure it is safe to light the torch for desoldering joints in a system from which a flammable refrigerant has been removed?


Working outdoors is sufficient
Such joints must never be desoldered; they must be cut with a pipe cutter
Purge the system with compressed air
Ensure good ventilation and check the work area with a flammable gas detector

30

Ťažká

How would you prepare a system containing 100 g of R1270 for debrazing, if local regulations allow controlled venting of small HC quantities?


Vent the R1270 outdoors and start brazing immediately
Recover the R1270 to a vacuum and start brazing immediately without a nitrogen purge
Vent the R1270 into the room and open a window
Vent the R1270 to a safe outdoor location, then purge with OFN three times (pressurise and vent), and braze with OFN flowing

31

Ťažká

Which method should NOT be used to locate an R290 leak?


An electronic leak detector designed for HFCs
An electronic detector for flammable refrigerants
Leak detection foam
Fluorescent dye and UV lamp (if approved by the manufacturer)

32

Ťažká

Why can’t recovery stations designed for HFCs be used with R600a?


They contain ignition sources
The recovery unit cannot withstand the working pressure of R600a
The low-pressure switch setting will not be suitable for R600a due to its lower operating pressure
The oil in the recovery unit is not soluble in R600a

33

Ťažká

According to EN 378, what is the maximum R1234ze(E) charge in a cold room measuring 5 m × 3 m × 2.5 m (LFL = 0.303 kg/m³, access category a, location class I, no additional measures)?


2.27 kg
227 kg
618 kg
6.18 kg

34

Ťažká

What type of refrigerant is R32?


Hydrofluorocarbon
Carbon dioxide
Hydrofluoroolefin
Hydrocarbon

35

Ťažká

What hazards do A2L refrigerants pose?


Lower toxicity, higher flammability
Higher toxicity, lower flammability
Lower toxicity, lower flammability (burning velocity ≤ 10 cm/s)
Higher toxicity, higher flammability

36

Ťažká

What hazard is associated with the combustion of HFO or HFC refrigerants?


Ozone is formed
Nitrous oxide is formed
Hydrogen fluoride (HF) is formed
Phosgene is formed

37

Ťažká

Approximately what compressor displacement is required for R600a compared with R134a for the same cooling capacity?


The same
About half
About twice as large
About seven times as large

38

Ťažká

What is the GWP value for R32 according to Regulation (EU) 2024/573?


3
675
7
0

39

Ťažká

Why is charge accuracy more important in critically charged R290 systems than in HFC systems?


Because R290 is only used in systems below 150 g
Because such systems never have liquid receivers
Because of lower operating pressures
The charge mass is much smaller than in an HFC system, because the liquid density of R290 is much lower

40

Ťažká

Why does the condenser fan run continuously in some systems using R1270?


To ensure that the discharge pressure never becomes excessive
To prevent the build-up of contaminants in the condenser
To dilute the refrigerant in the event of a leak
To reduce energy consumption

41

Stredne ťažká

What is the main design difference in hydrocarbon refrigeration systems?


The need to eliminate ignition sources and limit the charge because of the refrigerant's flammability
Higher operating pressures
No need for safety measures
Lower energy efficiency

42

Stredne ťažká

How do compressors used in hydrocarbon systems differ?


They must operate at higher pressures than HFC compressors
There is no difference
They must be approved by the manufacturer for the specific flammable refrigerant (e.g. electrical components that are not ignition sources, suitable oil)
They need no lubrication

43

Ťažká

What must the label of a flammable refrigerant cylinder include?


Only the refrigerant name
Information about the cylinder owner
Only the net weight
The refrigerant name, the UN number, the hazard label (e.g. 2.1 – flammable gas) and basic safety information

44

Ťažká

Why is the absence of a 'flammable refrigerant' label on equipment a serious hazard?


It reduces system efficiency
It may lead to the wrong oil being selected
It has no significant effect on safety
It may lead to the use of tools that are ignition sources

45

Ťažká

Which set of information on the label of a flammable refrigerant cylinder is crucial from a safety perspective?


Cylinder colour and date of manufacture
Name of the substance, hazard label (ADR) / GHS pictogram (CLP), UN number
Manufacturer’s name and country of origin
Gross weight and batch number

46

Ľahká

What is the requirement regarding the labelling of an installation containing a flammable substance?


Colour-coding of pipes is sufficient
The labelling must indicate the type of substance and the flammability hazard
Labelling is not required for hermetically sealed systems
Labelling is required only in technical rooms

47

Ľahká

What are the potential consequences of using unsuitable connections in a system containing a flammable substance?


Merely a reduction in efficiency
No impact on safety
Risk of leakage and the formation of an explosive mixture
Merely installation difficulties

48

Ťažká

What is the purpose of gas detectors in a room with a refrigeration system?


Measuring refrigerant temperature
Controlling compressor capacity
Monitoring pipe pressure
Early leak detection and triggering of measures preventing health risks and explosive atmospheres (alarm, ventilation, shut-off)

49

Ťažká

How often should gas detection sensors in a machinery room be checked?


Before every start-up of the unit
Once every 5 years
According to the manufacturer's instructions and regulations – at least every 12 months
Only after a leak has occurred

50

Ťažká

Where should a gas detector be located according to EN 378?


Where the refrigerant would accumulate: low (near the floor) for refrigerants heavier than air, high (near the ceiling) for lighter ones such as NH₃
Only at the room entrance
Anywhere in the room
Near the control panel

51

Ľahká

How should an employee respond when a gas alarm is triggered?


Carry on working until they see a leak
Switch off the system and wait for the alarm to stop
Leave the room immediately and notify their supervisor
Reduce the pressure in the system

52

Ťažká

What safety checks should be carried out when installing a new refrigeration system with a flammable refrigerant?


The presence of health and safety signage, adequate ventilation and gas detectors
The colour of pipes and hoses
Only the compressor power
Only that the air filter is new

53

Ľahká

Gas detectors should be installed in rooms where:


The amount of refrigerant exceeds a specified permissible threshold
The room is less than 5 m²
Ventilation is natural
Any refrigerant is present, regardless of the quantity

54

Ťažká

What are the requirements for emergency exits from a refrigeration machinery room?


In small machinery rooms emergency exits need not be signed
At least two exits are required and signage is optional
One exit with a sign stating the refrigerant type is sufficient
Outward-opening doors and signed escape routes (number of exits per the standard)

55

Ťažká

Which installation measure for a flammable-refrigerant system improves its energy efficiency?


A thorough tightness test and evacuation (dehydration) of the system
Restricting room ventilation
Omitting the filter-drier
Charging above the nameplate quantity

56

Ľahká

How do leaks affect systems using flammable refrigerants?


They cause refrigerant loss, reduced efficiency and a fire hazard
They improve efficiency
They lower the temperature
Have no effect

57

Ťažká

Why is it important to limit the refrigerant charge in HC systems?


It increases capacity
It limits the possibility of reaching a flammable concentration (≥ LFL) in a leak, increasing safety
It lowers the temperature
It doesn't matter

58

Ľahká

Why is the cleanliness of heat exchangers in HC systems important?


It increases the pressure
It doesn’t matter
It improves heat transfer and reduces energy consumption
Causes leaks

59

Ľahká

What maintenance measures improve the efficiency of a system using a flammable refrigerant?


Regular checks for leaks and operating parameters
Disabling safety devices
Lack of servicing
Increasing the refrigerant charge

60

Ľahká

How does the correct selection of components affect a system using a flammable refrigerant?


It ensures safe and optimal operation and minimises energy losses
It lowers the temperature
It doesn’t matter
It increases the amount of refrigerant

61

Ľahká

Why is it important to use the correct service tools in HC systems?


Causes leaks
It doesn’t matter
It increases energy consumption
It ensures operational safety and reduces refrigerant losses

62

Ľahká

How does pipe insulation affect the efficiency of systems containing HC?


Causes leaks
It reduces energy losses and improves efficiency
It doesn’t matter
It increases the pressure

63

Ťažká

What hazards are associated with a safety group A3 refrigerant?


Higher toxicity, no flame propagation
Higher flammability, lower toxicity
Lower toxicity, no flame propagation
Lower flammability, lower toxicity

64

Ťažká

What is the GWP of R32 (per AR4, as used in Regulation (EU) 2024/573)?


6
3922
0
675

65

Ťažká

What factors are taken into account when determining the maximum charge for comfort air-conditioning/heating applications?


Practical limit, height of the indoor unit, floor area
Lower flammability limit, room volume
Practical limit, room volume
Lower flammability limit, height of the indoor unit, floor area

66

Ťažká

What compressor displacement is required for R1270 compared with an R404A compressor in the medium-temperature range (cold room)?


About 1.5 times larger
About 6 times larger
About half
Similar

67

Stredne ťažká

What distinguishes class 2L refrigerants from class 2?


Heat of combustion above 19 MJ/kg
No lower flammability limit
A maximum burning velocity of no more than 10 cm/s
Higher toxicity

68

Stredne ťažká

What is the lower flammability limit (LFL) of propane R290?


Approx. 0.307 kg/m³
Approx. 0.38 kg/m³
Approx. 0.038 kg/m³ (approx. 2.1% by volume)
Approx. 1.8 kg/m³

69

Ťažká

What is the maximum R290 charge per circuit of a commercial refrigerating appliance (e.g. a cabinet) according to EN IEC 60335-2-89:2022?


1.5 kg
13 × LFL ≈ 494 g
150 g
1.2 kg

70

Ťažká

Calculate the maximum R32 charge (LFL = 0.307 kg/m³) for a wall-mounted air conditioner (h₀ = 1.8 m) in a 20 m² room using m_max = 2.5 × LFL^1.25 × h₀ × A^0.5.


approx. 1.5 kg
approx. 0.46 kg
approx. 4.6 kg
approx. 13.8 kg

71

Stredne ťažká

Equipment marked 'Ex II 3G' may be used in zone:


1
2 (explosive gas atmosphere unlikely and short-lived)
20 (dusts)
0

72

Stredne ťažká

How is explosion hazard zone 2 defined?


An explosive atmosphere is likely to occur in normal operation
An explosive atmosphere is present continuously or for long periods
An area where flammable refrigerants are never used
An explosive atmosphere is not likely in normal operation and, if it occurs, persists only for a short period

73

Stredne ťažká

Under which UN number is propane (R290) carried under ADR?


UN 1978
UN 3337
UN 3252
UN 1005

74

Ťažká

What is the maximum quantity of R290 (class 2, group F) that may be carried per transport unit under the ADR 1.1.3.6 exemption?


333 kg
20 kg
Unlimited
1000 kg

75

Stredne ťažká

At what concentration should a portable flammable gas detector used for R290 work raise an alarm at the latest?


No higher than 25% of LFL
At 100% of LFL
At 150% of LFL
At 5% propane by volume

76

Stredne ťažká

How should a recovery cylinder be prepared before filling it with a hydrocarbon refrigerant?


No preparation is needed
Purge it with compressed air
Partly fill it with nitrogen to 5 bar
Evacuate it (no air) and label it for the specific flammable refrigerant

77

Stredne ťažká

What is the correct approach in a risk analysis before work on an HC system?


Having a fire extinguisher is sufficient
The risk analysis is done after the work is finished
First select PPE, then possibly remove ignition sources
First eliminate hazard sources (e.g. ignition sources); where this is not possible, identify them and apply mitigating measures (ventilation, detection, PPE)

78

Ťažká

What is the charge limit m₃ = 130 m³ × LFL for R290 (LFL = 0.038 kg/m³) according to IEC 60335-2-40?


approx. 0.15 kg
approx. 4.94 kg
approx. 13 kg
approx. 0.99 kg

79

Stredne ťažká

Why must the charge of small, critically charged R290 systems be weighed to within a few grams during service?


Small charge deviations significantly change superheat/subcooling and efficiency, and overcharge increases the risk in a leak
Because R290 is more expensive than HFCs
Because scales are not needed – charging is done by sight glass
Because extra R290 improves efficiency